Q:As per earlier version from Merlin Trinoyoni, expected delivery date was Dec 2011. Now, they say that they can't hand over before April 2012. What is the exact reason?
Latest Answer: Hi All.
We have received the response from the Merlin authority for the above mentioned issues. I would request all of you to fix a time and sit together to discuss on the next step for giving them the response of the said letter.
Please find the response from the Merlin as follows :
Dear Sir,
With reference to your meeting held with our Project Manger Mr.Gagan Sanghvi,we would like to state as below:
You must sign the POA for formation of Association of apportionment of Tax in the record of KMC on or before
taking the final possession and not at the time of registration.
1. As because many flat owners would be doing the registration later on.
2. Possession will be handed over at the end of September'2012 and not in the 1st week of September'2012 as
mentioned by you.
3. Maximum capacity of load against individual meter has been mentioned in your MASD bills.
With Best Regards,
Harish Gupta
Manager-Accounts ( Customer)
--