sk, Apartment Resident, Hyderabad
Q: Does this project has a completion date? Every month they kept on moving the completion date by a month for the last 8 months..

My replies to this discussion
Last weekend I visited the site, only difference I could note is that they laid corridors flooring for 9-5 floors for D-block, which in a normal case would b one week work. I spoke to one of the agent over there - he responded saying if you are ready to pay complete amount, they will complete the flat but possession is not possible. Since govt will not gv elec & water till atleast 60% of building are registered.Last weekend I visited the site, only difference I could note is that they laid corridors flooring for 9-5 floors for D-block, which in a normal case would b one week work. I spoke to one of the agent over there - he responded saying if you are ready to pay complete amount, they will complete the flat but possession is not possible. Since govt will not gv elec & water till atleast 60% of building are registered.
My comments to replies
I am planning to take house in this venture..any suggestions, I understand the possession is getting late, apart from that so you see any issues
Hi Vinay, Quality seems to be good compared few other projects near by but if u r planning to change anything inside of house like flooring, they will not provide their quote. If you are planning to buy as flat as they give without any modifications and not looking for immediate occupation then it is ok to go.
1st November 2012

Hi SK, have you purchased flat in Divya sree Shakthi? Or are you planning to buy one? I guess it is nearing completion now..
Hi Gireesh, There are hardly 15-20 people working in appartments. Since last 6 months, there isn't any progress in construction. They had been promising everyone that it will be ready in next 2 months. Once you make the payment..forget it.
28th October 2012

Q: Is anyone planning to meet the management regarding the completion date? If yes do post when you are planning.. They promised Sept'12 to me andnow they say if I am ready to pay full amount they complete the construction flat but cannot promise occupancy.

My comments to replies
Without occupancy certificate it is unsafe to take possession.. all buyers have to unite together and demand for your rights..
Yes Mr.Verma, but you will get occupancy certificate only when atleast 60% of the flats gets registered.
30th October 2012

Q: Can anyone please tell me that after paying full amount they are ready to give possesion or after that they still extend the possession date
My replies to this discussion
Once u make full payment builders are liable to provide u possession as per bye-laws. Already a family is living in 3 BHK-1560sft in 5th floor. It is just that we need to push DSG management for occupancy. Once u make full payment builders are liable to provide u possession as per bye-laws. Already a family is living in 3 BHK-1560sft in 5th floor. It is just that we need to push DSG management for occupancy.