Q: Lodha’s Casa Univis projects under construction at Bhayanderpada, along the Ghodbunder road, 15 km from Thane city. The TMC had pointed out to the major irregularities as RCC structures were built without plinth certificates or in some cases additional floors were constructed without approval of the town planning department. The Lodha group was found to have violated norms in seven instances and in one case, the TMC bureaucrat said, a 10-storied building was constructed without any approvals. “The file was submitted by their architect but our officials were requested by them notto process the files for the time being. However, on site, the builder had gone ahead and built the building without any permissions,’’ the official said. Municipal commissioner RA Rajeev said several other builders were fined for violation of development control rules and confirmed that penalty amounting to crores was recovered from the two builders. “We initiated action under the Maharashtra Regio

My replies to this discussion
Yes, the message has another option of continuing with the project till completion - which could take another 22 months or so. Yes, the message has another option of continuing with the project till completion - which could take another 22 months or so.
This portal does not have user-friendly interface. Let us connect on email. My email id is ajay.bettoli@gmail.comThis portal does not have user-friendly interface. Let us connect on email. My email id is ajay.bettoli@gmail.com
Q: Hi All, I contacted Lodha today and was informed by Vivek Koshti that the possession date for Ceilo C is going to be further postponed to May 2014. They will be sending the letters/email to all the customer next week. This is due to not getting approvals from TMC. They also informed that they are not planning to pay any compensation/interest payment for the delayed possession as the reason for delay is beyond builders control. I booked the flat in 2009 and have been paying the interest on loan to bank for last 2 years. I am not comfortable to continue paying further cost for Lodha not managing the project efficiently. I am planning to seek legal options for what can be done in this scenario apart from going to consumer court. I will appreciate if you guys can let me know if you have received any communications from Lodha on this and if you are planning to take any legal action. Thanks

My comments to replies
I think it would be a good Idea to share your emails so that we can can in touch further to get our contact nos. I can be accessed at sraj2099@gmail.com
my email id is ajay.bettoli@gmail.com
31st January 2013

Q: Stalled construction of CASE Univis Cielo C building. If it is due to TMC not providing the permit, what is it that the builder has violated that has compelled the TMC take such action? Is there a way to find out what is the real reason with TMC directly and also whether there is any legal way out builder can take corrective action to resolve the problem? This way we will know whether the building construction is stopped for ever or not.

My replies to this discussion
Hope builder of such repute will let down his customer espcially when he is launching phase II of the project. Hope builder of such repute will let down his customer espcially when he is launching phase II of the project.
Correction ... I meant will not let down.Correction ... I meant will not let down.
So far it has been via email - with those who have shared their email ids and contact details. We are also jointly exploring the options. I think we should get a hang of extent of problem which has prevented progress of construction. We need to listen to what Lodha has to say/offer to resolve the problem, gauge Lodha's intertest level/impact on brand image to resolve problem, and take a call on further course of action based on response. Coming to the first step there more questions than answers at the moment-Who in TMC should be approched? Will TMC entertain queries from us or expect us to file RTI. If it is RTI, we need to understand the process. Any help /advise in getting the facts first will be helpfulSo far it has been via email - with those who have shared their email ids and contact details. We are also jointly exploring the options. I think we should get a hang of extent of problem which has prevented progress of construction. We need to listen to what Lodha has to say/offer to resolve the problem, gauge Lodha's intertest level/impact on brand image to resolve problem, and take a call on further course of action based on response. Coming to the first step there more questions than answers at the moment-Who in TMC should be approched? Will TMC entertain queries from us or expect us to file RTI. If it is RTI, we need to understand the process. Any help /advise in getting the facts first will be helpful
My comments to replies
PLEASE GET IN TOUCH WITH MR. SUHAS SAMANT - DEPUTY CITY ENGINEER (TOWN DEVELOPMENT & PLANNING) ESTATE, Email - Dcetdo@ThaneCity.Gov.In
Thanks for the response. Will explore the option you have suggested
27th January 2013