Q:
I have purchased a flat in Cilantro in Year 2012 with a promise of getting possession on Dec 2013. Obviously the project is not complete and the completion date is not known. I feel KP is not being transparent of the issues and just keep giving random completion dates. Is anyone else in the same boat as me? I am NRI and just could not keep up with these false promises. Anyone for help?
Please don't buy the property before verifying all the clearances...
Sushant, I have also been promised with the Dec 2013 dates and still no concrete reply from the builder...I am trying to connect to the builder again and again but no final dates are being communicated...Answers like 10-12th floors clearance for building 1 are taking the time...
Thats exactly correct. What they told me is- Building E will be 9 Floors only for not getting clearance. Thus they changed my payment plan to match 9 floors as opose to original 11 floors. So as of now i have paid 80% + of the total value. The constrution work is just at a stand still. I called one of the rep two days ago and i was asked to wait until next week for the update. This Sucks- i invested in Kolte Patil property based on the Name!!! Please dont fool people Mr. Kolte Patil
11th February 2014
Hi Sushant.
Got in touch with executive and heard that the construction work in under way and will take 2 years to complete from now. Most probably possession will be around June 2015.
Well- They have 4 buildings in Cilantro. The Construction of 2 building adjoining each other have started out of which one is structually completed till 9th floor and other 1st. Second bulding is stuck at 1st floor due to non issuance of Environmental clearance, however 1st one is told me to be ok. So on the agreement i am given the possession date of Dec 2013. I am clueless with June 2015 you mentioned!
13th January 2014