Q: I have booked a flat in an under-construction redevelopment project in Mumbai. Its a 17 floor tower but at the time of booking they had CC only till 12th floor and they had applied CC again for further floors. My flat is on 4th floor, its been almost 7 months but they havent still got the CC while the construction work is stalled as 12th slab is completed. Just last month builder said, he has got a new IoD for all floors and CC will e issued soon. My query is, does builder get CC in parts or there might be some issue with the permission for upper floors? And does IoD needs to be reapplied because he already had the IoD earlier when he started the construction.

My replies to this discussion
hey umesh, you have any updates on the status of the project? still no signs of any work.hey umesh, you have any updates on the status of the project? still no signs of any work.
thnx for response. do you know why there is a delay and what is the response have you got from the developer?thnx for response. do you know why there is a delay and what is the response have you got from the developer?
My comments to replies
I booked in 2011 May. I guess it was dec 2015. After grace period March 2016. Now builder should pay interest after that..
Hi Umesh, as you are also a buyer in the same property, it would be nice to connect with you and understand what update you have got from the builder. If you don't mind can you drop me an email with your contact details at: mrkothari@gmail.com.. Thanks!
20th May 2016

Hi Mukesh, The IOD approval and demolition of the building will be followed by the issue of the CC (plinth level) by the MCGM which shall enable the Developer to start the construction work and after the plinth lines are verified by the MCGM officers, the further CC is granted for the complete building.
in my case, builder has not got CC for all floors after plinth. he got CC for only 12 floors and now CC is awaited for upper 5 floors.. which has caused construction to be stalled by 7-8 months. so my query is, do builder's take CC in parts?
18th May 2016

Ask a Question