Q:While buying the flat builder promise ample water supply..said in case KDMC fail to supply water we have boring which can provide ample water supply.Now when there is shortage of KDMC water builder says that the complete topgraphy of a Raunak city does not boring system...there are rock underneath the whole property..borinf not possible..they simply fooled us..I request all you people not to buy Raunak city any flats in phase 2,3 or4
Q:I have booked a flat with Raunak city kalyan. My agreement says the possession date of June 2015 and am waiting for possession. There is hardly any movement on the project from the time i booked it and when i have visited now, I am having a bad experience with them
Latest Answer: Hi all,
Phase-3 posession has been delayed to December 2015 now. But seeing the current status of construction work which is on hold. They have told me that construction work will start from August 2015 but no work has not yet started. Now, they are saying that possession will be June 2016. I don't no when will the construction work be started.
Q:Even I had very bad experience with Raunak till now. I have booked flat in 2012 and it was assured that i will get possession in 2013. Now it is September 2015 but still I am struggling to get possession. I have to keep visiting site everyday. Now they are again making delay in possession even after taking maintenance for the full September-2015 month and advance for quarter. All the officers point fingers to some other person to contact and they do not have proper coordination. He will assure the work will be done in next day and once you visit again still its at same condition. For many of the things they will ask to contact Thane office. It is not feasible to visit Thane everytime as I am staying in Kalyan and i am sure many people booked flat here staying around Kalyan. I dont understand if they have complete project in Kalyan why they cant provide entire service from Kalyan office itself. There was tiles break in leaving room just in entrance, when i asked to replace they have replaced with different shades and it is easily visible. Now they are making arguments to replace with same colour. I have made all payments and now facing lot of issues in getting possession with proper work. Also they have assured me possession in May-2015, based on that I have selled my existing flat and they were unable to provide possession and at the last moment i have to shift in rented flat. It is really worst experience till now with Raunak.
Latest Answer: Kailash..plz send your mob no on 9900011817..we have also booked flat in raunak. we have made a group on whatsup..its helping us to getting updates..u can join there
Latest Answer: Raunak City Phase 3 Whatapp Group already started - If anyone interested to join please send me msg on my mobile number +91 9819518429